Layham Road Sports Ground Pavilion

This page aims to provide you with the most up to date information on the project and outcomes achieved for the rebuilding of the pavilion at Layham Road Sports & Recreation Ground.

All decisions are made via Full Council and can be viewed in the minutes of meetings.

Project update

2024 updates:

  • Tender applications were analysed and the contract awarded to Hutchinsons for £828,785.53.
  • The build start date is likely to be end of July / beginning of August now due to general elections delaying funding confirmations.

2023 work completed:

What else happened in 2022?

  1. Councillor Questions June 2022
  2. Agenda Item 10 LRSG Project Questions Report 18.08.2022 (002) report Full Council
  3. Hadleigh Town Council joined the Football Foundation Framework

What was achieved in 2021?

  1. Architects have completed our plans for a full size 3G pitch located at the Layham Road Sports Ground.
  2. Architects have prepared draft plans for the new sports pavilion
  3. We have completed a Program of Use based upon the needs of Hadleigh Football and Rugby Clubs and other local clubs and organisations who have already registered their interest in using the new facilities. The Programme of Use indicates full utilisation of the 3G can be expected on weekday evenings and at weekends. Members of the public and other organisations will be able to register their interest in using the facilities at other times.
  4. In preparation for the demolition of the old pavilion that was damaged by fire in 2020 we have put in place temporary changing rooms, a shower unit and toilets to allow the continued used of the pitches and tennis courts at Layham Road Sports Ground whilst the new facilities are developed. We are very grateful and thank the Hadleigh Scouts leaders for granting the Town Council permission to locate the temporary units on their land.
  5. We have made the old pavilion building safe and ready for demolition and installed a new power distribution unit in readiness to feed the new facilities.
  6. Costs for our plans and the Layham Road Sports Ground Sub Committee received.
  7. LRSG 7th Dec update

The Working Group was dissolved and a Sub-committee created in it’s place on 17th June 2021. The sub-committee had helped get the project started and prepare the architect’s brief and design considerations. The sub-committee has now been suspended (July 2022) until a time that it may required in the future. All decisions have to be made by Full Council and now a monthly project update along with any decisions is taken to Full Council meetings.

1
PDFNameSize
Thumb Pavilion-Business-Plan-for-funding.pdf Pavilion Business Plan for funding.pdf

Open Download Copy Link 967.44 KB 2024-08-16 16th August 2024 2024-08-16 16th August 2024
967.44 KB
Thumb Improving-facilities-survey-results.pdf

Open Download Copy Link 19.9 KB 2022-11-22 22nd November 2022 2022-07-28 28th July 2022
19.9 KB
Thumb 5295-0102-P02-Proposed-Site-Plan.pdf

Open Download Copy Link 1.37 MB 2022-11-22 22nd November 2022 2022-01-14 14th January 2022
1.37 MB
Thumb 3G-AGP-Vision-V2-Public.pdf

Open Download Copy Link 136.3 KB 2022-11-22 22nd November 2022 2022-11-22 22nd November 2022
136.3 KB

4

2fcfd2427b

All minutes from the sub-committee are below:

1
PDFNameSize

4

2fcfd2427b